Phase 2A & 2B
Project Update Timeline
August 2023
Schematic Design (SD)
The SD was submitted to the City in August 2023. Approved by City with minor comments.
Completed
January 2024
Design Development (DD)
The Design Development Phase started, and various other consultants were contracted by the Architect. They include civil, structure, landscape, mechanical, plumbing, electrical, IT, Public Address, and Fire Alarm/Fire Suppression System.
Completed
March 2024 – October 2024
Construction Document (CD)
Following completion of DD Phase the CD Phase started and completed by October 2024.
Completed
October 2024 – TBD
Plan Review 1 (PR1)
Following completion of CD Phase the CD Documents were submitted to City for Plan Review.
In Progress
January 2025 – TBD
Plan Review 2 (PR2)
Following the CD submittal first round of Plan Review Comments were received January 06, 2025. The Design Team is currently working on responses to comments and revising drawings as applicable.
In Progress
Upcoming Phases
TBD
Plan Building Permit
Once the Plan Review is completed and CD approved by City an Application for Building Permit will be filed.
TBD
Plan Bidding Phase
Once the BP is issued the CD will be released for Bid to three pre-qualified Contractor.
Phase 2A – TBD
Construction Phase
Once the Contractor is selected Phase 2A Construction will start and be completed.
Phase 2B – TBD
Construction Phase
Once Phase 2A is completed the Phase 2B Construction will start and get completed.